Question: 3 : 2 8 7 4 2 . Construct a network diagram for the project below, determine the float / slack for each activity, and

3:28
74
2. Construct a network diagram for the project below, determine the float/slack for each activity, and then identify the critical path. How many days are needed to complete the project?
\table[[Activity,Task time (in days),Preceding activities],[A,2,None],[B,4,A],[C,5,None],[D,4,A],[E,5,A],[F,6,C],[G,4,C],[H,7,D],[I,2 I,D],[K,5,B, E. II]]