Question: 3 . 2 . End item A has a planned lead time of 2 weeks. There are currently 1 2 0 units on hand and

3.2. End item A has a planned lead time of 2 weeks. There are currently 120 units on hand and no scheduled receipts. Compute the planned order releases using lot-for-lot and the MPS shown here:
\table[[Week,1,2,3,4,5,6,7,8,9,10],[Demand,41,44,84,42,84,86,7,18,49,30]]
3.5. Rework Problem 2 with 50 units of safety stock. What is different from Problem 2?
 3.2. End item A has a planned lead time of 2