Question: 3 . 2 . End item A has a planned lead time of 2 weeks. There are currently 1 2 0 units on hand and
End item A has a planned lead time of weeks. There are currently units on hand and no scheduled receipts. Compute the planned order releases using lotforlot and the MPS shown here:
tableWeekDemand
Rework Problem with units of safety stock. What is different from Problem