Question: 3 2 . Moving from an aggregated plan to a master production schedule requires Disaggregation Rough cut capacity planning Sub - optimization Strategy formation
Moving from an aggregated plan to a master production schedule requires
Disaggregation
Rough cut capacity planning
Suboptimization
Strategy formation