Question: 3. (20 POINTS) A product development project is planned to contain the activities shown in the table below, along with their required completion times and

3. (20 POINTS) A product development project is planned to contain the activities shown in the table below, along with their required completion times and precedence. (a) Draw the CPM network diagram for the project, labeling all activities and times. (b) Perform a forward pass and backward pass through the network to determine the critical path, the expected duration of the project, and the slack time for each activity Activity Activity time (weeks) Immediate predecessor 5 5 ,6 7,8,9
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
