Question: 3 . 3 3 points EX 8 - 7 ( Algo ) You have prepared the following schedule... You have prepared the following schedule for
points
EXAlgo You have prepared the following schedule...
You have prepared the following schedule for a project in which the key resource is a tractor. There are three tractors available to the project. The resource requirements are as shown in the diagrams below. Develop a resourceconstrained schedule. Use the parallel method and heuristics given. Be sure to update each period as the computer would do
Use the following order of heuristics: Minimum slack, Smallest duration. Lowest identification number
Schedule resourte load dhart with E and slackupdates
Note: Recall, in the schedule resource load chart the timeconstrained scheduling interval ES through LF has been shaded. Any resource scheduled beyond the shaded area will delay the project. TP stands for time period.
How long will the project take if it was NOT resourceconstrained?
How long will the resourceconstrained project take?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock