Question: 3 - 3 6 . Find the average time per unit required to produce the first 3 0 units, if the slope parameter of the

3-36. Find the average time per unit required to produce
the first 30 units, if the slope parameter of the learning
rate is 92% and the first unit takes 460 hours.
(a)330.693(b)305.5404(c)245
(d)347.3211