Question: 3 . 4 0 - A project has been defined to contain the following list of activities along with their required times for completion. Activity

3.40- A project has been defined to contain the following list of activities along with their required times for completion.
Activity no. immediate Activity time(weeks) predecessors
1 collect requirements 3
2 Analyze Processes 21
3 Analyze data 22
4 Design Processes 62
5 Design data 33
6 Design screens 23,4
7 Design reports 44,5
8 program 56,7
9 test and documents 77
10 install 28,9
Draw a network diagram for the activities.
Calculate the earliest expected completion time.
Show the critical path.
What would happen if activity 6 were revised to take six
weeks instead of two weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!