Question: 3 - 5 2 . Under normal operating conditions a zone has a total cooling load of 1 2 0 , 0 0 0 B

3-52. Under normal operating conditions a zone has a total cooling load of 120,000Btuhr(35kW)
with a SHF of 0.8. The space is to be maintained at 74F(23C)db and 50% relative humidity
(RH). However, there are periods when the latent load is high and the SHF is estimated to be
as low as 0.6. Assume that air enters the cooling coil at 85F(29C)db and 71F(22C)wb and
the coil apparatus dew point is 48F(9C).(a) Devise a system and the associated psychro-
metric processes to cover the necessary range of operation. (b) Define the various air states and
show the processes on Chart 1a.(c) Compute air-flow rate, coil load, minimum zone load, and
anv reheat that mav be required. Assume constant air flow and standard sea-level pressure. Please solve only a and b
3 - 5 2 . Under normal operating conditions a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mechanical Engineering Questions!