Question: 3 . 8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
tableACTIVITYIMMEDIATE PREDECESSORSTIME DAYSABCADAEB CFDGE F
a Develop an AON network for this problem.
b What is the critical path?
c What is the total project completion time?
d What is the slack time for each individual activity?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
