Question: 3. A system T has two periodic tasks: { T = T = (10, 5), T= T2 = (14,6). (a) is the system T schedulable


3. A system T has two periodic tasks: { T = T = (10, 5), T= T2 = (14,6). (a) is the system T schedulable according to the RMA principle? (b) Suppose task T2 is more important than task T1. Use the period transformation approach to modify the task set so that the periodic tasks are schedulable. Draw a timing diagram to show the RMA-based schedule of the tasks. B TI 0.5 2 3 5. u bluu vuonnon 00 7 8. 9 11 115 12 12.5 13 13.5 15 Nano 17.5 18.5 195 205 21 22.5 23.5 245 25 25. 265 27.5 285 8 0.5