Question: ( 3 ) Canvas cannot be computed with the giv Question 3 4 pts A manager decides to design a production line for a job

(3) Canvas
cannot be computed with the giv
Question 3
4 pts
A manager decides to design a production line for a job with 3 tasks. The task times are 0.5 minutes, 1.4 minutes, and 0.7 minutes What is the cycle time in minutes, for a single production line with no parallel activities?
0.5
0.867
1.4
2.6
0.7
Question 4
4 pts
Amber Ale uses a simple five-step process to prepare its products for shipment. Because of recent increases in demand, the company is setting up an assembly line to do the work. If Amber Ale needs a new product off the line every 10 minutes, what would be the efficiency of this line balancing?
\table[[Task,Precedence,Time (mins)]]
 (3) Canvas cannot be computed with the giv Question 3 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!