Question: 3 Check my we Variable manufacturing overhead Standard Quantity 0.6 Standard Standard Rate Unit Cost $0.80 $0.48 25 points During August, LLL had the following
3 Check my we Variable manufacturing overhead Standard Quantity 0.6 Standard Standard Rate Unit Cost $0.80 $0.48 25 points During August, LLL had the following actual results eBook Hint Units produced and sold Actual variable overhead Actual direct labor hours 24,100 $ 9,400 15,100 Print ce Required: Compute LLL's variable overhead rate variance, variable overhead efficiency variance, and over- or underapplied variable overhead (Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (.e., zero variance).) Variable Overhead Rate Variance Variable Overhead Efficiency Variance Variable Overhead Spending Variance