Question: 3. Complete Exercise #6 on page 315. Identify the critical path for the network in Exercise #5. How long should the project take? 5. Calculate
3. Complete Exercise #6 on page 315. Identify the critical path for the network in Exercise #5. How long should the project take?
5. Calculate early start, early finish, late start, late finish, and float for each of the activities in the network below. The duration of each activity is given. A flowchart shows a series of activities along with duration. The flowchart starts with A (Duration: 12) which is branched into, activities B (Duration: 4) and D (Duration: 7). The activity B points to activity C (Duration: 1) which along with activity D points to activity E (Duration: 3 ). 6. Identify the critical path for the network in Exercise 5. How long should the project take