Question: 3. Computing department is planning to install new computer systems in one of the lab. Several things must be done to make sure the system

3. Computing department is planning to install

3. Computing department is planning to install new computer systems in one of the lab. Several things must be done to make sure the system works properly before all the accounts are put into the new system. All the process are named as activities from A to F. The following table provides information about this project. How many weeks will it take to install the system? What is the critical path? (25 marks) ACTIVITY IMMEDIATE PREDECESSORS TIME (DAYS) 0:0 A 5 B A C D C 7+a 6+b 3 + a 4+ a + d 5+a+e b=3 d=9 e=1 E B,D F C