Question: 3. Consider a Multilevel Queue scheduler with two queues, numbered 1 and 2. Queue 1 has higher priority over queue 2. Both queues use RR

 3. Consider a Multilevel Queue scheduler with two queues, numbered 1

3. Consider a Multilevel Queue scheduler with two queues, numbered 1 and 2. Queue 1 has higher priority over queue 2. Both queues use RR scheduling. Time Quantum: To, -3, TO-4 Process Burst Time Arrival Priority Queue 12 P2 4 P4 12 18 10 Draw Gantt chart. Find average turnaround time, average waiting time