Question: 3. Consider a project for which AoN network and associated crash data are given as follows. Budget for crashing the project is limited to 5

3. Consider a project for which AoN network and

3. Consider a project for which AoN network and associated crash data are given as follows. Budget for crashing the project is limited to 5 thousand dollars. Define your decision variables and construct an LP model in open mathematical form to find minimum project crash completion time with available budget. B D S A T E Activity A 12 Normal Time Cost Time (Days) (thousand $) (Days) 8 6 4 7 5 5 9 8 6 12 9 8 15 10 12 Crash Crash Cost Cost Allowable Per Day (thousand $) Crash Days (thousand $) 4 1.5 9 2 2 3 2 18 4 2.25 16 3 2 14 B D E