Question: 3. Cost plus incentive fee Target cost Target fee Sharing ratio over run Sharing ratio under run Actual cost 800000 50000 85/15 70/30 800000

3. Cost plus incentive fee Target cost Target fee
3. Cost plus incentive fee Target cost Target fee Sharing ratio over run Sharing ratio under run Actual cost 800000 50000 85/15 70/30 800000