Question: 3. Cycle time =1.3 minutes; the maximum time each workstation has is 1.3 minutes. Use the longest task time heuristic. a) Balance the line (fill
3. Cycle time =1.3 minutes; the maximum time each workstation has is 1.3 minutes. Use the longest task time heuristic. a) Balance the line (fill out the table below) using the longest task time heuristic: If more than one task is eligible, choose the longest task if enough remaining time exists. For the first workstation, eligible tasks are A,C, and E. b) What is utilization (efficiency)? c) What is the idle percentage (balance delay)