Question: 3 days Purchase Wood 5 days Purchase Select Design Plot Paint EN Foundation Where is the lag time in this network diagram? Between Dig Foundation

3 days Purchase Wood 5 days Purchase Select Design Plot Paint EN Foundation Where is the lag time in this network diagram? Between "Dig Foundation" and "Lay Foundation" Between "Purchase Plot" and "Select Design" There is no lag time represented Between "Harden Foundation Cement" and "Assemble Shed" 3 days 6 days Lay Assemble Shed Foundation