Question: 3. Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a merge activity? (10 marks) Activity Description

3. Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a merge activity? (10 marks) Activity Description Predecessors A . Contract signing None Questionnaire design A Target market ID A D Survey sample B, C E Develop presentation B F Analyze results D G Demographic analysis H Presentation to client E, F, G U OUI
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock