Question: 3 . For a project you are familiar with create a WBS . Identify all of the major components and provide three levels of detail.
For a project you are familiar with create a WBS Identify all of the major components and provide three levels of detail.
Given the following information below:
Activity Duration Predecessors
A weeks Start
B weeks Start
C weeks Start
D weeks A
E weeks B
F weeks C
G weeks F
H week A
I weeks DEG
J weeks F
K weeks DEGH
A Determine the Critical Path and Project Duration.
B What is the slack time float for activities A B G and J
How would you go about scheduling resources for a project? Give specific examples and explain why you use your approach.