Question: 3. For the network shown: A(5) (B(10) ACTIVITY C(8) NORMAL TIME ABCDEFG 5086744 D(6) b. a. Determine the critical path and the early completion time
3. For the network shown: a. Determine the critical path and the early completion time in weeks for the project. b. For the data shown, reduce the project completion time (crash) by three weeks. Assume a linear cost per week shortened, and show, step by step, how you arrived at vour schedule. Hint: Create 2 columns: Time Available to Crash and incremental Crash Cost. Use the formula NT - CT to determine "Time Available to Crash", To determine the Incremental Crash Cost, use the formula (CC - NC)/Time Avaliable to Crash. This will tell you the cost/week to crash each activity