Question: 3. From the table provided below draw the network diagram and complete the additional table for the earliest start and finish times along with the

3. From the table provided below draw the network

3. From the table provided below draw the network diagram and complete the additional table for the earliest start and finish times along with the latest start and finish times for each node or activity. Identify the critical path along with the project's completion time or duration. Immediate Predecessor(s) Activity A Time (Weeks) 3 B 4 D 6 9 E 6 A B B CD D, E GF F G H 6 8 9 Earliest Start Earliest Finish Latest Start Latest Finish Slack Activity A B D E F G H