Question: 3. Gale Construction was awarded a contract to construct two major freeways in Edmonton at a total contract price of $ 10,000,000. The estimated total

 3. Gale Construction was awarded a contract to construct two major

3. Gale Construction was awarded a contract to construct two major freeways in Edmonton at a total contract price of $ 10,000,000. The estimated total costs to complete the project were $ 8,000,000, and it is expected to take two years. Using the percentage-of-completion method: a. Prepare the journal entry to record construction costs of $ 4,400,000 for the first year. b. Prepare the journal entry to record progress billings of S 5,000,000 for the first year. c. Prepare the journal entry to recognize the revenue and gross profit for the first year. d. What balances are left on the balance sheet at the end of the first year and what do they tell the financial statement users? Debit Credit 2 (

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!