Question: 3 ) GreenTech is managing a solar panel installation project for a commercial building. The project manager, Lisa Green, is concerned about delays because some
GreenTech is managing a solar panel installation project for a commercial building. The project manager, Lisa Green, is concerned about delays because some tasks have unpredictable durations. The following table shows the optimistic time a most likely time m and pessimistic time b for each activity all in days along with their immediate predecessors: Assignment begintabularlllllhline Activity & Optimistic Time a & Most Likely Time m & Pessimistic Time b & Immediate Predecessorshline A & & & & hline B & & & & hline C & & & & hline D & & & & A hline E & & & & B C hline F & & & & D E hline G & & & & D hline H & & & & F hline I & & & & G hline J & & & & H I hline endtabular a Calculate the expected time and variance for each activity using the PERT formulas: b Construct the project network and determine the expected project completion time and the critical path. c Compute the expected values for Earliest Start ES Earliest Finish EF Latest Start LS Latest Finish LF and slack for each activity. d Assuming activity durations are independent and normally distributed, calculate the probability that the project will finish in days or less.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
