Question: 3 ID A B D E F G H Activity Order review Order standard parts Produce standard parts Design custom parts Software development Manufacture custom

3 ID A B D E F G H Activity Order review Order
3 ID A B D E F G H Activity Order review Order standard parts Produce standard parts Design custom parts Software development Manufacture custom hardware Assemble Test Predecessor Time None 5 A 1 A 10 9 A 42 C D 15 B, F 10 E, G 9 10 points eBook References days The project will take The critical activities are The late start on Activity C is The slack on Activity Cis The slack on Activity Dis The early start on Activity is days. days. days. days