Question: 3. Job A, B, C, D, and E must go through Processes I and II in that sequence (i.e. Process I first, then Process II).

3. Job A, B, C, D, and E must go through

3. Job A, B, C, D, and E must go through Processes I and II in that sequence (i.e. Process I first, then Process II). Use Johnson's rule to determine the optimal sequence to schedule the jobs to minimize the total required time. Job Required Processing Time on! 4 Required Processing Time on II 5 A B 16 14 C 8 7 D 12 11 E 3 9