Question: 3 . Lupin, a construction company, are evaluating the selection of five projects over a 3 - year planning horizon. For this purpose, their total
Lupin, a construction company, are evaluating the selection of five projects over a year
planning horizon. For this purpose, their total available budget is million and they decide the
equal allocation of the budget over years. The following table gives the expected profits for each
project and the associated yearly expenditures.
Projects Expenditure in millions year Profits in
Year Year Year millions
Now Lupin wants to maximize its profit. Based on the information given above, answer the following
questions.
a Write down the objective function of the Integer programming consistent with the objective of
Lupin
b Write down the constraints of Integer programming consistent with the objective of Lupin
c Which projects should be selected? What will be the maximum return for Lupin? You can use
either excel or QM for windows to solve the problem
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock