Question: 3) Make a comparison between two different proposals, using present worth (PW) with i=12%, which one should be selected. Draw cash flow with your submission.
3) Make a comparison between two different proposals, using present worth (PW) with i=12%, which one should be selected. Draw cash flow with your submission. System initial cost Annual cost Salvage cost Life in years -190,000 EGP +31,000 EGP/yr +155,000 EGP 10 -220,000 EGP +41,000 EGP/yr +175,000 EGP 10