Question: ( 3 marks ) c ) A project consists of seven activities A , B , C , D , E , F , G

(3 marks)
c) A project consists of seven activities A,B,C,D,E,F,G. The precedence relationships and time estimates are as follows:
\table[[Job precedence,Duration in weeks],[A,,2,5,8],[B,A,6,9,12],[C,A,5,14,17]]
2
\table[[D,B,5,8,11],[E,GD,3,6,9],[F,-,3,12,21],[G,EF,1,4,7]]
ii) Determine the expected job duration and variance of each job. (5 marks)q,
iii) What is the expected length of the project and its variance?
(4 marks)