Question: [:3 Moving to another question will save this response. Question 14 A project has the following statistics: AC = $50,000, VAC = $2,500, ETC =

 [:3 Moving to another question will save this response. Question 14

[:3 Moving to another question will save this response. Question 14 A project has the following statistics: AC = $50,000, VAC = $2,500, ETC = $68,500 BAC = $121,000 and EAC = $118,500. What is the forecasted cost to complete this project? 0 A. $50,000 0 B. $118,500 0 c. $121,000 0 D.$68,500