Question: 3. Net present value method Aa Aa Consider the case of Sutherland Engineering: and Engineering is evaluating a proposed capital budgeting project that will require

3. Net present value method Aa Aa Consider the case of Sutherland Engineering: and Engineering is evaluating a proposed capital budgeting project that will require an initial investment of $156,000. The project is expected to generate the following net cash flows Year 1 Year 2 Year 3 Year 4 Year Cash Flow $43,000 $51,400 $47,700 $46,400 Assume the desired rate of return on a project of this type is 11%. What is the net present value of this project? O-$18,163.50 O -$10,100.92 O $10,285.40 O -$15,358.30 Suppose Sutherland Engineering has enough capital to fund the project, and the project is not competing for funding with other projects. Should Sutherland Engineering accept or reject this project? O Reject the project O Accept the project