Question: 3 . Part X routing is machine A , then B , and then C; 1 0 0 , 0 0 0 parts are to

3. Part X routing is machine A, then B, and then C; 100,000 parts are to be produced per year. Part Y routing is machine B, then A, and then C; 200,000 parts are to be produced per year. Given the following, what are the machine fractions for machines A, B, and C to pro- duce parts X and Y? Part X standard time Part Y standard time Part X defect estimate Part Y defect estimate Historical efficiency Reliability factor Equipment availability Machine A 0.15 hr 0.10 hr 5%5%85%95%1600 hr/yr Machine B 0.25 hr 0.10 hr 4%4%90%90%1600 hr/yr Machine C 0.1 hr 0.15 hr 3%3%95%85%1600 hr/yr