Question: 3 points 7. Freemont Inc. started work on a construction contract in 2015. The contract price is P40 million. However, if the cumulative inflation rate

3 points 7. Freemont Inc. started work on a construction contract in 2015. The contract price is P40 million. However, if the cumulative inflation rate exceeds 10%, the contract price shall be increased by 20%. Cost escalations on the contract are probable as to recovery. The following information is presented. What is the realized gross profit for 2016? * * Costs incurred to date Estimated cost to complete Cumulative inflation rate 2015 P9,600,000 14,400,000 15% 2016 P18,000,000 6,000,000 22% A. P5,600,000 B. P8,400,000 C. P9,600,000 D. P18,000,000