Question: ( 3 points ) A new project involves the construction of columns in a building. A total of 3 0 different columns need to be
points A new project involves the construction of columns in a building. A total of different columns need to be constructed. It takes one worker an average of hours to construct one column. Also, assume hour workdays.
a If workers are assigned to the task of constructing the columns, determine the productivity columnsday for all workers working together. Assume the productivity rate for one worker when they work alone is the same as when they work with the other workers.
b What duration nearest whole day should be assigned to the activity to construct the columns for all columns using workers?
c How many more workers are needed to decrease the activity duration calculated in Part b by Use the actual duration calculated in Part b not the duration rounded to the nearest whole day.
points An engineer predicts that designing the formwork for precast concrete girders will require an average of hours. The time needed fluctuates due to variations in girder designs and differences in the engineers' productivity. The durations follow a normal distribution with a standard deviation of hours.
a What is the probability that the engineer will complete the design of the formwork for all of the girders in hours or less?
b What is the probability that the designs will take no more than hours?
c When planning the design activity, what activity duration in hours should be used to provide an level of confidence that the duration will not be exceeded?
points Based on historical project data, a contractor estimates that it typically takes an average of days to complete the formwork for concrete walls, with a standard deviation of days. This variability is attributed to factors such as weather conditions, worker performance, and sitespecific impacts. It is assumed that the activity durations follow a standard normal distribution.
a What is the probability that the duration to construct the formwork for all of the walls will take longer than days?
b After the formwork is constructed, the wall reinforcing will be installed and then the concrete placed. These three activities will be performed in series ie finishtostart relationships For this part, use the following values:
Formwork construction:
Rebar installation:
days, days
days, days
days, days
Place and cure concrete:
What is the probability that all three activities will be completed in a total of days or less? Hint: Use the mean, standard deviation, and variance for the entire path similar to the process used for PERT
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock