Question: ( 3 points ) A new project involves the construction of columns in a building. A total of 3 0 different columns need to be

(3 points) A new project involves the construction of columns in a building. A total of 30 different columns need to be constructed. It takes one worker an average of 14 hours to construct one column. Also, assume 8-hour workdays.
a. If 3 workers are assigned to the task of constructing the 30 columns, determine the productivity (columns/day) for all workers working together. Assume the productivity rate for one worker when they work alone is the same as when they work with the other workers.
b. What duration (nearest whole day) should be assigned to the activity to construct the columns for all 30 columns using 3 workers?
c. How many more workers are needed to decrease the activity duration calculated in Part (b) by 30%? Use the actual duration calculated in Part (b), not the duration rounded to the nearest whole day.
(3 points) An engineer predicts that designing the formwork for 32 precast concrete girders will require an average of 120 hours. The time needed fluctuates due to variations in girder designs and differences in the engineers' productivity. The durations follow a normal distribution with a standard deviation of 1.84 hours.
a. What is the probability that the engineer will complete the design of the formwork for all of the girders in 124 hours or less? (P124)
b. What is the probability that the designs will take no more than 118 hours? (P118)
c. When planning the design activity, what activity duration (in hours) should be used to provide an 85% level of confidence that the duration will not be exceeded?
(3 points) Based on historical project data, a contractor estimates that it typically takes an average of 20.0 days to complete the formwork for 30 concrete walls, with a standard deviation of 1.55 days. This variability is attributed to factors such as weather conditions, worker performance, and sitespecific impacts. It is assumed that the activity durations follow a standard normal distribution.
a. What is the probability that the duration to construct the formwork for all of the walls will take longer than 22 days?
b. After the formwork is constructed, the wall reinforcing will be installed and then the concrete placed. These three activities will be performed in series (i.e., finish-to-start relationships). For this part, use the following values:
Formwork construction:
Rebar installation:
=20.0 days, =1.55 days
=7.25 days, =0.50 days
=9.50 days, =0.70 days
Place and cure concrete:
What is the probability that all three activities will be completed in a total of 35 days or less? Hint: Use the mean, standard deviation, and variance for the entire path (similar to the process used for PERT).
( 3 points ) A new project involves the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!