Question: 3 points Save Ans As an engineering professional you were assigned to complete the following analysis of investment alternatives and select the preferred altenative. The
3 points Save Ans As an engineering professional you were assigned to complete the following analysis of investment alternatives and select the preferred altenative. The study period is three years and the MARR-15 % per year Alternative A $11,000 4,000 250 5,000 850 Alternative B $16,000 6,000 300 6,150 Capital Investment Annual Revenues Alternative C $13,000 5,540 Annual Cost Market Value PW(15%) 400 2,800) 577 Do nothing Alternative A Alternative B Alternative C $10,740