3) ProPainters hires students at $100 a week to paint houses. It leases equipment at $1000 a week. The table sets out its total product schedule.
Labour Output
(students) (houses painted per week)
1 2
2 5
3 9
4 12
5 14
6 15
a. If Propainters paints 12 houses a week, calculate its total cost, average total cost, and marginal cost.(3)
b. At what output is average total cost a minimum?