Question: 3 Question 3 (15%) You are deciding on whether or not to crash your project. After asking your operation manager to conduct an analysis, you

3
Question 3 (15%) You are deciding on whether or not to crash your project. After asking your operation manager to conduct an analysis, you have highlighted the precrash and postcrash activity durations and costs of a project, shown in the following table. Assuming all the activities are on the critical path, calculate the slope of crashing each activity. Which activity would you crash? Why? Show your work. Page 2 Activity Normal Duration days 6 Immediate Predecessors B C Cost $ 150 640 750 9 Crashed Duration Cost days $ 3 350 4 1000 1 1000 9 5000 3 900 4 1500 2 B D 11 3500 700 A AC E 6 F 5 1000 B G 10 6000 6 8000 DEF