The activities illustrated in Table represents the coding of the mobile app and the physical
construction of the solar electrical panels. Implementation will occur from January start
time: day and end on February end time: day
Table : The label, description, and start time and end time of activities that inform the design and
eventual launch of the solar information system.
Activity label Activity description Start day End day
A Coding of mobile app
B Physical assembly of solar panel units
C Testing of solar panel information systems
D Quality assurance of solar information systems
E Launch of solar information systems
Illustrate the activities listed in Table on a Gantt diagram. Adopt the layout illustrated in Figure
Figure : Gantt diagram layout
Activities A and B are in a finishtofinish dependency relationship, which means Activity A
cannot finish until Activity B finishes. However, notice that Activity A coding of mobile app is
not dependent on Activity B physical assembly of solar panel units to start. Explain why
Activity A is not dependent on Activity B to start.