Question: 3 . The activities illustrated in Table 3 represents the coding of the mobile app and the physical construction of the solar electrical panels. Implementation

3. The activities illustrated in Table 3 represents the coding of the mobile app and the physical
construction of the solar electrical panels. Implementation will occur from 1 January 2024(start
time: day 1) and end on 29 February 2024(end time: day 49).
Table 3: The label, description, and start time and end time of activities that inform the design and
eventual launch of the solar information system.
Activity label Activity description Start day End day
A Coding of mobile app 837
B Physical assembly of solar panel units 1537
C Testing of solar panel information systems 3348
D Quality assurance of solar information systems 3348
E Launch of solar information systems 4949
3.1. Illustrate the activities listed in Table 3 on a Gantt diagram. Adopt the layout illustrated in Figure
1.(14)
Figure 1: Gantt diagram layout
3.2. Activities A and B are in a finish-to-finish dependency relationship, which means Activity A
cannot finish until Activity B finishes. However, notice that Activity A coding of mobile app is
not dependent on Activity B physical assembly of solar panel units to start. Explain why
Activity A is not dependent on Activity B to start.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The question seems to be split into two parts illustrating activities on a Gantt chart and explaining the dependencies between activities A and B Lets ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!