Question: 3. The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about
3. The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing.
(a) What is the crash cost for 8 hours of time-savings?
(b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?
Activity
Normal
Duration (hours)
Normal
Cost ($)
Crash
Duration (hours)
Crash
Cost (S)
Immediate
Predecessors
A
2
10
2
0
None
B
3
15
2
23
A
C
5
25
4
30
B
D
3
20
1
24
C
E
6
30
4
45
C
F
1
5
1
0
C,E
G
7
35
6
50
F
H
10
50
7
62
D,G
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
