Question: 3) The data below represent time study observations for an assembly operation. Assume a 7% allowance factor. What is the normal time for each element?

3) The data below represent time study observations for an assembly operation. Assume a 7% allowance factor. What is the normal time for each element? What is the standard time for the assembly operation? Observations (times in minutes) Element Performance Rating 1 2 3 4 5 1 100% 1.5 1.6 1.4 1.5 1.5 2 90% 2.3 2.2 2.1 2.2 2.4 3 115% 1.7 1.9 1.9 1.4 1.6 4 100% 3.5 3.6 3.6 3.6 3.2