Question: 3. The results from a working sampling study of a work force are divided into 12 categories. This sample covers a snanaran 8-hour days a.

 3. The results from a working sampling study of a work

3. The results from a working sampling study of a work force are divided into 12 categories. This sample covers a snanaran 8-hour days a. What are the pereentages per category? b. What are the expected hours per category? c. If 1200 pieces were manufactured during the work sampling and Categories 1-6 are the categories that actively make the pieces, what is the standard time assuming 80% performance rating and 15% PFD? How many paid FTEs are needed for these operations. Non Productive rate is 15% d. If the hourly rate is $22.50 and benefits is 22%, what is the labor cost annually

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To address this problem lets tackle each part step by step a Percentages per Category First calculate the percentage of observations for each category Formula Percentage Number of Observations in Cate... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!