Question: 3) The Tacoma Company allocates overhead based on a predetermined overhead rate of $8.00 per direct labor hour. Job B 689 required 6 tons of
3) The Tacoma Company allocates overhead based on a predetermined overhead rate of $8.00 per direct labor hour. Job B 689 required 6 tons of direct material at a cost of $900.00 per ton and took employees who earn $15.00 per hour a total of 90 hours to complete. What is the total cost of Job B 689? (12.5 points) Direct Material Cost (4 points) Direct Labor Cost (4 points) MOH cost (4.5 points)