Question: 3. Tom Seed, project manager for Seeds Elevator, used data from previous projects to provide times for the seven activities needed to revitalize elevators. Using
3. Tom Seed, project manager for Seeds Elevator, used data from previous projects to provide times for the seven activities needed to revitalize elevators. Using Toms data, complete the following:
| Activity # | Mt | Ot | Pt | Expected time |
| 1 | 4 | 1 | 7 |
|
| 2 | 4 | 1 | 10 |
|
| 3 | 5 | 3 | 11 |
|
| 4 | 5 | 4 | 6 |
|
| 5 | 5 | 2 | 8 |
|
| 6 | 10 | 9 | 17 |
|
| 7 | 4 | 3 | 8 |
|
- Expected time for activity 2
- Expected time for activity 6
- Based on the information from Seeds Elevator in problems #3, which activities HAVE slack?