Question: 3. Tom Seed, project manager for Seeds Elevator, used data from previous projects to provide times for the seven activities needed to revitalize elevators. Using

3. Tom Seed, project manager for Seeds Elevator, used data from previous projects to provide times for the seven activities needed to revitalize elevators. Using Toms data, complete the following:

Activity #

Mt

Ot

Pt

Expected time

1

4

1

7

2

4

1

10

3

5

3

11

4

5

4

6

5

5

2

8

6

10

9

17

7

4

3

8

  1. Expected time for activity 2
  2. Expected time for activity 6

  1. Based on the information from Seeds Elevator in problems #3, which activities HAVE slack?

SOLVE Q#4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!