Question: 3 . Use the largest eligible task technique to assign the tasks to workstations. Fill in # 1 - # 5 below to show the
Use the largest eligible task technique to assign the tasks to workstations. Fill in ## below to show the assignments of tasks to workstations in order. Also, fill in the table to show which tasks are assigned to each workstation but note that not all workstations are needed!
Hint #: When assigning tasks to workstations, note that you can assign a task to the same workstation as its predecessor if there is time at the workstation. For example, suppose task C is the only predecessor of task F C must come before F and C is already assigned to Workstation Then, if task F will fit in the allowed time at Workstation you can assign F to workstation along with C; and you just do C before F