Question: 3. When adding resources to a project and having employees work overtime are not effective, what other ways do we have to manage risk as
3. When adding resources to a project and having employees work overtime are not effective, what other ways do we have to manage risk as it is happening? a. Ending the project and creating a new project b. Delaying the project and reducing the project's scope c. Incentive packaging and maintenance assessment d. Prioritization and reducing the project's scope