Question: 3. You are given the activity information below and the activity-on-node precedence diagram for a project at your company. 16 points (-4/error) a) Determine the

3. You are given the activity information below
3. You are given the activity information below
3. You are given the activity information below and the activity-on-node precedence diagram for a project at your company. 16 points (-4/error) a) Determine the critical path and its duration. What is your initial estimate for project completion time? Show your work on the next page. b) Fill in the table on the next page to determine the earliest start (ES) time, the earliest finish (EF) time, the latest start (LS) time, the latest finish (LF) time, and the Slack for each project activity. Slack = LS -ES or LF-EF. Activity Time (days) Immediate Predecessor(s)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!