Question: 3. Zenith Corporation uses the weighted-average method in its process costing system. It produces prefabricated flooring in a series of steps carried out in production

3. Zenith Corporation uses the weighted-average method in its process costing system. It produces prefabricated flooring in a series of steps carried out in production departments. All of the material that is used in the first production department is added at the beginning of processing in that department. Data for May for the first production department follow:

Percent complete

Units

Materials

Conversion

Work in process inventory, May 1

5,000

100%

30%

Work in process inventory, May 31

10,000

80%

10%

Materials cost in work in process inventory, May 1

$1,500

Conversion cost in work in process inventory, May 1

$4,000

Units started into production

180,000

Units transferred to the next production department

200,000

Materials cost added during May

$54,000

Conversion cost added during May

$252,000

  1. Calculate the first production departments equivalent units of production for materials and conversion for May.
  2. Compute the first production departments cost per equivalent unit for materials and conversion for May.
  3. Compute the first production departments cost of ending work in process inventory for materials, conversion, and in total for May.
  4. Compute the first production departments cost of the units transferred to the next production department for materials, conversion, and in total for May.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!