Question: 30. Project HIJ has three negative risks and one positive risk. Based on the probability and impact for each risk, what contingency reserve should be

30. Project HIJ has three negative risks and one positive risk. Based on the probability and impact for each risk, what contingency reserve should be established? (The brackets indicate negative impact) Risk Probability Impact A 15% ($5,000) B 30% ($7,500) C 50% ($2,000) D 20% $3,000 $3,200 $3,400 $3,600 $4,000 tigate