Question: 30 _ to create a network, you must a. Calculate the float for each activity. b. Identify all loops through activities. c. Identify the party

30 _

to create a network, you must

a.

Calculate the float for each activity.

b.

Identify all loops through activities.

c.

Identify the party responsible for each activity.

d.

Understand the activity precedence.

27 _

For large projects, network diagrams are more useful if they are completely detailed.

a.

False

b.

True

25 _

we crash the project duration because :

a.

The project has slipped behind schedule.

b.

That the initial schedule may be too pessimistic.

c.

Market needs change and the project is not in demand any more.

d.

There are no repercussions for delivering the project late.

22 _

Measurement of project performance should include a clear definition of:

a.

The reporting relationships among members of the project team.

b.

The project baseline.

c.

What to measure.

d.

Trigger points.

18 _

For a burst activity in a backward pass, the largest succeeding late start becomes the late finish for that node.

a.

True

b.

False

Clear my choice

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!